GATE 2018 Architecture and Planning (AR) solved question paper
1.In Critical Path Method (CPM) for time scheduling, ‘forward pass calculation’ is carried
out for determining
(A) Late start and early finish time (B) Early start and early finish time
© Late start and late finish time (D) Early start and late finish time
2.In mass transportation, LRTS stands for
(A) Light Rail Transit System
(B) Linear Rail Transit System
© Light Rail Transportation System
(D) Linear Rail Transportation System
3.Assuming other variables remaining constant, the Tropical Summer Index
(A) Increases with increase in air velocity
(B) Decreases with increase in wet-bulb temperature
© Decreases with increase in globe temperature
(D) Increases with increase in vapour pressure
Detailed GATE 2018 Architecture and Planning (AR) solved question paper can be downloaded from the link attached
1.In Critical Path Method (CPM) for time scheduling, ‘forward pass calculation’ is carried
out for determining
(A) Late start and early finish time (B) Early start and early finish time
© Late start and late finish time (D) Early start and late finish time
2.In mass transportation, LRTS stands for
(A) Light Rail Transit System
(B) Linear Rail Transit System
© Light Rail Transportation System
(D) Linear Rail Transportation System
3.Assuming other variables remaining constant, the Tropical Summer Index
(A) Increases with increase in air velocity
(B) Decreases with increase in wet-bulb temperature
© Decreases with increase in globe temperature
(D) Increases with increase in vapour pressure
Detailed GATE 2018 Architecture and Planning (AR) solved question paper can be downloaded from the link attached